Call now: +254 723 477 035 Email: info@kariukiwaweru.com

December2020

#MrsW’shouse – Week 7

Material blue gum poles 3*2 timber 5*6 timber 10 sheets marine boards 6*1 timber 75kgs 3″ nails 300 metal trappers In week 7 the contractor started preparing for the slab- to be done in week 8 they started by placing the 3*2 poles on the shortest side of the room.[…]

Read More »